The Ottawa River boathouse is a remarkable structure designed by architect C.P. Meredith, and constructed between 1914 and 1925 for the Ottawa New Edinburgh Canoe (ONEC) Club. It has been the site of canoeing, boating and recreational activities for nearly a century.

In 2010, the ONEC Boathouse was designated a Recognized Federal Heritage Building because of its links to the history of canoeing in Canada, its architectural value as a rare example of early boathouse design, and its remarkable setting on the river.

About the project

The Ottawa River boathouse revitalization project will bring required repairs and upgrades to this heritage property, and provide new opportunities for public access and shoreline animation. The work outlined below, which will be undertaken from July 2019 to July 2020, is aimed at the reopening of the club by rehabilitating the base building for adaptive reuse in all four seasons.

Building envelope

Work to preserve the heritage character of the boathouse, and allow four-season use of the two upper levels, will include the following:

  • the conservation, repainting and reinstatement of the existing wood siding;
  • the introduction of a standard exterior wall assembly, including thermal insulation, continuous water, air and vapour barriers, and interior drywall;
  • the conservation of viable heritage windows for reuse on the club level, which will continue to be for three-season use;
  • the installation, on the two upper floors, of new windows of a design that is compatible with the historic character, but that provides the required thermal performance.

Universal accessibility

The building is located on a water lot, and the lowest “occupied” floor, the club level, is below the 100-year flood plain. This presents a challenge for the integration of accessibility within all levels, interior and exterior. The universal accessibility improvements will maintain the essence of the building’s use and function, and will include the following:

    • converting an existing parking lot into universal accessible parking;
    • providing a safe crossing of the Sir George-Étienne Cartier Parkway for all users;
    • creating a universally accessible path from the parkway to the pedestrian bridge landing;
    • raising the pedestrian bridge to the original hall level;
    • installing an elevator inside the building to allow access to the three main levels of the building.

    Replacement of the pedestrian bridge

    The existing bridge and foundation have reached the end of their life cycle. They have been deemed unfit for repair and reuse, and will be replaced.

    A new, prefabricated bridge made of Corten steel, compatible with the nautical and transportation style of the boathouse facility, will be installed at the bridge’s historic level. The new bridge will also have a longer span to reach the escarpment, which will facilitate the creation of universally accessible pathways from the parkway to the new raised bridge landing.

    The bridge will also feature a custom guard rail which is a contemporary reinterpretation of the historical wood balustrade of the building.

    Public services

    Site service upgrades will include the following:

    • new sanitary services out of the flood plain;
    • electrical service upgrades;
    • municipal water connection for potable water;
    • a new sprinkler system as a part of the fire protection upgrades.

    Public Participation

    Please sign up for the project newsletter for in-depth information and timely updates on upcoming work.


    Closures and detours

    The following traffic management plan will be in place during the work:

    This work is part of the NCC’s major infrastructure projects funded by the Government of Canada’s $55- million investment announced in the 2018 federal budget.