Monday, July 29, 2019 7:00 am to Thursday, November 21, 2019 5:00 am


On Monday, July 29, 2019, the Municipality of Chelsea, in collaboration with the National Capital Commission (NCC), will begin rehabilitation work and the addition of bike lanes in both directions on de la Mine Road.

The work will continue until November 21, 2019. The work schedule is 7 am to 5 pm, subject to weather conditions and operational constraints.

During the work, only local traffic will be permitted. Detours will be marked with traffic signs.

Between Monday, August 26, and Wednesday, September 4, de la Mine Road will be closed to traffic completely to allow for planned culvert replacement work. 

Residents and visitors are asked to obey existing traffic signs, to protect the safety of all concerned and to avoid slowing the work. For more information about this project, please visit the Municipality of Chelsea road works web page, or email info@chelsea.ca.